I promise (hopefully) only a few more house updates to go. Sorry this one is so late, the start of school distracted me a bit.



Not too much on the outside has changed since that last post, but busy bees have been working hard on the inside!
**They installed the furnace and of the heating ducts (it looks like there is gigantic spider in the attic).

**The electrician finished wiring and putting all of the outlets, lights, and switch boxes in.


**They put in the tub in the master bath.


**We had it prewired for satellite and cable.

**They poured the porch, driveway, and sidewalks. **We finished buying light fixtures (we hope!).

**We finalized the choice for the tile in the master bath.

**They framed where the fireplace will sit.

**We started packing so the move would be easier since school was starting. The APT looks like a maze of boxes!

Everything had to be inspected before they were supposed to start putting insulation in today. Hopefully drywall and paint isn't too far in the future!